New types of optimization problems are faced by the generating companies that operate on deregulated electricity markets.
The characteristics of these problems depend on the various market structures. In the framework of the recently settled Italian
electricity market, one of these new problems is the transition from hourly energy programs, defined by the market, to more
detailed power generation dispatches, defined for intervals of 15 min. Such a more detailed plan is needed on the one hand
by the national system operator (Terna, Rete Elettrica Nazionale) for the assessment of power system stability and security,
and on the other hand by the power plant operators for its implementation. The transition procedure should respect the hourly
energy constraints and take the main operating constraints of the generating units into account. The paper presents possible
solutions of the problem through linear optimization models and reports computational results on real-world instances.
Keywords Electricity market - Energy program - Linear programming
MSC classification 90C90 - 90B30 - 91B74 - 90C05